Yallourn Mine
Yallourn's open cut mine extracts approximately 18 million tonnes of brown coal per annum and 4 million cubic metres per annum of overburden, utilising four coal dredges, one overburden dredge, and over 20kms of coal and overburden conveyor.
Scope of Work
Total maintenance and plant asset managment of three conveyor systems and four bucket wheel excavators. Yallourn Energy is currently in the transition of moving from bucket wheel excavators for coal mining to slope mining using bulldozers and feeder breakers.
Achievements
Mobiled within one month with no loss of coal supply
50% reduction in maintenance cost/tonne in the first year
overburden production increased by 26% due to increased efficiency
coal supply reliability improved from 99.8% to 99.95%
PROJECT DETAILS
Location
Latrobe Valley, Victoria
Client
TRUenergy
Scope of Work
Total maintenance and plant asset management of three conveyor systems and four bucket wheel excavators. Yallourn Energy is currently in the transition of moving from bucket wheel excavators for coal mining to slope mining using bulldozers and feeder buckets.
Schedule
2002 - ongoing